Inner Bell

A commercial building just over 7,000 square feet, framed for H&C Construction from a complex, hardware-heavy set of prints.

Inner Bell — framing by Glacier Basin Builders in Eureka, MT

Just over 7,000 square feet of commercial building, framed for H&C Construction in eight days. This was a complex build — a complicated set of prints with a lot of structural hardware to place correctly, and a schedule that didn’t leave much room for error.

The crew ran 16-hour days to hit the timeline. It was a high-stress job given the complexity of the plans, but the framing came together fast once everyone found their rhythm on site.

Coming in to help another builder get a difficult structure framed and out of the ground on a tight schedule is exactly the kind of work this crew is built for.

Location
Eureka, MT
Timeline
Framed start to finish in eight days, working 16-hour days.
Materials
  • Commercial frame construction
  • Heavy structural hardware

Challenges

The prints were complicated and hardware-intensive, and the schedule put the crew under real time pressure — met with long days (16-hour shifts) to keep the eight-day framing timeline.

Result

Fully framed on schedule despite a demanding print set and compressed timeline.